Date:


The Federal Executive Council (FEC) presided over by Vice President Yemi Osinbajo has approved the variation order for the East West road project sections 1-4 from N246 billion to N506 billion.

Laolu Akande, Senior Special Assistant to the President on Media and Publicity, Office of the Vice President, briefed State House correspondents after the FEC meeting on Wednesday at the Presidential Villa, Abuja.

Akande said that the Minister for works and Housing presented a memo in line with Federal Government’s continued engagement in bringing succour and resolving issues around the recent flooding.

“He got approval for the variation order in respect of repair works on the East West road project affected during the recent flooding occurrences in the Niger Delta.

“So, the approval was for a variation order for the East West road project sections 1-4 from Warri to Port Harcourt, Eket, Oron, including Oron-Eket bypass in the sum of N260 billion, thereby increasing the total contract sum for the outstanding sections 1-4 of the East West road projects from the sum of formerly of N246 billion now to N506 billion.

“The memo was approved.’’

Akande said that the Minister for Works and Housing got approval for the award of contracts for the urgent repairs, and special general maintenance of a few roads nationwide.

He said the approval included the construction of Gogora Guru Road in Yobe state, in the sum of N40 billion, with the completion time of 36 months.

“He also got approval for the rehabilitation of the 90 kilometre Buni Gari Gulani road also in Yobe state in the sum of N4 billion with a completion period of 36 months.’’

The senior special assistant added the minister got approval for urgent repairs in some roads also for the reconstruction of water cooperation, drive at Trinity Avenue Victoria Island Lagos state.

“That too was also approved in the sum of N2 billion with a completion period of 36 months.’’

He added that the minister also got approval for the award of contract for the dualisation and reconstruction of the Kano-Kwana-Ganja-Adeja road in Kano and Jigawa States, section Kano to Salu.

“This was approved in the sum of N94 billion inclusive of 7.5 per cent VAT with a completion period of 24 months,’’ he said.

Facebook Comments Box

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Share post:

Subscribe

Latest

More like this
Related

Army Adopts Standardised System to Improve Accountability and Discipline

The Nigerian Army has stepped up efforts to improve...

Students at OAU Threaten Shutdown, Plan Protest Over Unmet Demands

Students of Obafemi Awolowo University, Ile-Ife, under the Great...

Senate urges FG to boost surveillance, contact tracing over new COVID‑19 case

  The Senate on Tuesday called on the federal government...

Gunmen Kill Pastor, Family of Four in Fresh Plateau Attack

Gunmen have reportedly attacked Gako Village in the early...

Human Rights Centre Reacts to Killing of Ogidi Mena, Calls for Accountability and Justice in Delta

The Centre Against Injustice and Domestic Violence (CAIDOV) has...

Nigerian Navy Dismisses Officer Over Disobedience, AWOL

The Nigerian Navy has dismissed a rating identified as...

Army Admits ‘Mistake’ in Killing of NYSC Member in Abuja — Father

The father of a National Youth Service Corps member...

Ekiti Council of Elders to Include Younger Affiliates for Modernisation

The Ekiti Council of Elders has announced plans to...